After a few relatively quiet updates, we have a lot of information to share this week. Most notably, we have finalized our go live schedule, which is outlined on the migration portal. We will review this schedule with Governing Board as well as at upcoming technical group meetings and during our next all-staff webinar. We also have some data updates to share as well as details on how to request PowerPAC customizations.

With a little over three months to go until we migrate to Polaris, it's more important than ever to keep up to date on the project. Forward this email to your colleagues, or have them subscribe.

Keep your questions and data issues coming. We appreciate all of your efforts on this project.

In This Issue

Dates & Deadlines

Complete list of deadlines

Go Live schedule

  • February 2

  • Last day for policy addition requests

  • March 1

  • Last day to submit PAC changes to CCS

  • March 15

  • Last day to submit data testing issues

  • April 5

  • Last day to make add or change settings on Polaris test

  • April 6

  • Patron Address Cleanup completed by 9:00 PM