Migration Update: February 16, 2018

Libraries have one month left to submit data testing issues to CCS. by March 15th, all data issues should be reported so CCS and Polaris can clear outstanding issues prior to go live. Thursday, April 5th, 5:00 PM, is the last day to make changes to the training database for settings/templates/import profiles. This also includes PAC customization. Changes made to the training database in these areas prior to April 5th at 5:00 PM will carry over to the production data on April 17th. CCS will be reviewing the go live schedule in detail at technical group meetings, on library visits, and in our February 28th webinar. Review it now on the migration portal.
In This Issue
Dates & Deadlines
March 1
Last day to submit PAC changes to CCS
March 15
Last day to submit data testing issues
Submit planned changes to acquisitions practices
April 5
Last day to make add or change settings on Polaris test, including PAC
April 6
Patron Address Cleanup completed by 9:00 PM